Project Notifications

26 Sept, 2024
26/09/24 Suspicious Communications

All correspondence or direct engagement with residents living close to the Clonfad Solar Project site is always carried out by members of the Statkraft team.

2 Sept, 2024
Milestone Achievement - Grid Transformer Delivery

Last Friday marked a significant milestone for our ambitious 174MW Clonfad Solar Farm project - the successful delivery of our state-of-the-art grid transformer.

22 Jul, 2024
Traffic Management Update

Traffic Management Update: Delivery 

Scheduled to start the week commencing Monday 22nd July 2024.

29 Jun, 2024
Letter to residents: On-site Works

We recently circulated a letter to residents around the Clonfad area informing them of the commencement of works to construct this solar project.

 

See letter to Clonfad Solar residents here

16 May, 2024
On-site Works

Ramming Works commencing – Mid May 24”  and will be ongoing during the coming months

General construction works commencing in various locations across the site with the establishment of site roads & entrance ways etc ongoing.

16 May, 2024
Concrete pouring notification

As part of the development process of the permitted Clondfad Solar Project, we recently informed residents, by way of a letter drop in the local area, that we would soon be starting the initial stages of enabling works for construction.