Shronowen Solar & Wind

You may also be aware of the Shronowen Wind Farm project which received planning in September 2022. Both Shronowen Solar (this proposal) and the Shronowen Wind Farm were acquired by Statkraft from EMPower in January 2024.

 

  Shronowen Solar Shronowen Wind
Planning Status Planning to be submitted in 2025 Planning secured in September 2022
Technology Involved 108 MW - peak solar 10 turbines producing 45 MW
Substation No Yes
Biodiversity management plan Yes. Will be available to view with all other planning documentation once submitted to Kerry County Council Yes. It is available to view here on the Kerry County Council website:
https://www.pleanala.ie/en-ie/case/309156
Community Benefit Fund circa.  € 175,000 a year circa.  € 302,000 a year