Construction Start

Project Works Update

  • Duct installation works are now complete on the public roads.

Component Delivery Update

  • Main component deliveries are ongoing.

Turbine Install Update

  • Erection of turbines are planned to commence in Late July and continue over a 3-month window.

Planned Works August – September

  • Cable installation is planned for August/September.

Final Road Resurfacing – Weather Dependent

  • Final road surfacing to take place in October which will involve some short-term road closures, details of which will be posted here and distributed locally by letter closer to the time.

 

Turbine being transported to Monavane