Construction Start
Project Works Update
- Duct installation works are now complete on the public roads.
Component Delivery Update
- Main component deliveries are ongoing.
Turbine Install Update
- Erection of turbines are planned to commence in Late July and continue over a 3-month window.
Planned Works August – September
- Cable installation is planned for August/September.
Final Road Resurfacing – Weather Dependent
- Final road surfacing to take place in October which will involve some short-term road closures, details of which will be posted here and distributed locally by letter closer to the time.