Notifications
Minimal night works will be undertaken on 1st & 2nd of May.
- Works are progressing at pace on site to deliver this 42.3MW Project
- Ramming works are nearing completion
- Framework and Purlin install to follow in Sept/Oct
- Install of Panels begins in Sept
- Estimated completion of piling works:
- Continuing works – Ramming / Piling will continue, commencing after 8am daily, Monday to Saturday 8am to 1pm.
- It is envisaged that these works will be completed by the end of July 2023.
We recently distributed the letter attached below to residents living in proximity of the Harlockstown Solar Energy Farm.
This letter is to advise you, in advance of enabling works scheduled to commence at
the Harlockstown Solar Park, that access to the site is at the location of the exisitng
agricultural access on the R125 Regional Road.
With this in mind I would like to introduce myself, Suzanne O Leary, Community Liaison Officer for this project and your point of contact.
Engagement with the local community throughout all phases of development is very important to us. I am available to provide further information on the ongoing construction works, answer queries from residents, and engage with members of the local community.
I will be on site on a weekly basis and should you have any queries please feel free to contact me directly on 057 9379036.
We appreciate your patience during the construction of this project